Assembled trestle scaffold
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- Steel pipe, 3 months or less, 1 tier, 2m
- Unit
- set
- H2 2026 Unit Price
- 131,789 KRW
- Labor Ratio
- 71 %
Unit Price Definition
① Includes labor costs, material costs, incidental materials (braces, horizontal ledgers, handrail posts, handrails, wheels, jacks, etc.), and charges required for scaffolding installation and dismantling. ② The basic scaffold frame (post) shall conform to H1700×W1219, with an installation height of 2m or less per set. ③ This unit price applies to a scaffolding use period of 3 months or less.
Unit Price Adjustment
- If the scaffold installation height exceeds 2m, apply by multiplying the following coefficients. 3 months or less Assembled trestle scaffold 1 tier (2m) 2 tiers (4m) Standard market unit price 1.00 1.58 Labor ratio 1.00 1.05
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.