H-pile insertion after drilling (excavation type)
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- Less than 500mm, ℓ=10m or less
- Unit
- pc
- H2 2026 Unit Price
- 195,417 KRW
- Labor Ratio
- 55 %
Civil works
AE11* H-pile insertion after drilling / excavation type
Search in Explorer
Original Notice
Unit Price Definition
① This is based on the work of inserting H-piles after drilling (diameter less than 500mm) using dedicated drilling equipment. ② It includes work preparation, drilling, pile insertion, finishing, and cleanup. ③ Splicing (welding) work for H-piles is excluded. ④ It includes the costs of dedicated drilling equipment, air compressor, generator, and crane (for short-distance transport and insertion). ⑤ The purchase and transportation costs of H-pile materials are excluded. ⑥ The application criteria are as follows. - Drilling length (ℓ) : drilling length by each specification - Soil type : soil (clayey soil and sandy soil) - Casing : not used
Unit Price Adjustment
- This unit price is based on cases where no interference occurs from adjacent facilities (houses, railways, roads, etc.) and sufficient space is secured for standing the pile. - Apply by multiplying the following coefficients according to the construction scale. Classification Standard market unit price Labor cost ratio Construction quantity 50 pcs or more 1.00 1.00 Construction quantity less than 50 pcs 1.07 1.00
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.