Steel sheet pile (sheet pile) extraction (electric)

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
Type4, ℓ=13m or less
Unit
pc
H2 2026 Unit Price
88,349 KRW
Labor Ratio
63 %

Unit Price Definition

① This is based on the work of driving or extracting steel sheet piles using an electric vibratory pile hammer. ② It includes work preparation, pile driving and extraction, and finishing and cleanup work. ③ Pile splicing (welding), fabrication and installation of guide beams, and on-site fabrication of wedge-shaped piles, etc. are excluded. ④ It includes the costs of the vibratory pile hammer, crane, and generator. ⑤ Material purchase and transport costs, and the cost of an auxiliary crane for short-distance transport are excluded. ⑥ The application criteria for pile driving or extraction are as follows. - Driving/extraction length (ℓ) : Length for each specification - Soil type : Cohesive soil - Pile specifications shall conform to the following. Specification Remarks Steel sheet pile Type3 400 × 150 × 13 Steel sheet pile Type4 400 × 170 × 15.5

Unit Price Adjustment

- This unit price is based on cases where no interference occurs from adjacent facilities (houses, railways, roads, etc.) and sufficient space is secured for standing the piles. - Apply by multiplying the following coefficients according to the construction scale. Category Standard market unit price Labor ratio Construction quantity 100 piles or more 1.00 1.00 Construction quantity less than 100 piles 1.06 1.00

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.