BD221.10000

Copper pipe indoor general piping

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
∅125mm
Unit
m
H2 2026 Unit Price
40,596 KRW
Labor Ratio
91 %

Unit Price Definition

① This is based on indoor general piping using copper alloy pipes. ② Based on use of a self-propelled aerial work platform (scissor type). ③ Includes inserts (formwork inserts), installation of support steelwork, cutting, piping (tack welding), and piping test. ④ Costs for pipe jointing and sleeve installation are excluded. ⑤ Material costs for copper pipes, inserts, support steelwork, and pipe fitting accessories (elbows, reducers, flanges, adapters, tees, etc.) are excluded. ⑥ Equipment usage fees for cranes, forklifts, etc. for moving the aerial work platform are excluded.

Unit Price Adjustment

- If use of an aerial work platform is not possible, apply by multiplying the above unit price and labor cost ratio by the coefficients in the table below. Category When aerial work platform is not used Standard market unit price 1.16 Labor cost ratio 1.06 - Depending on the installation location, apply by multiplying the above unit price and labor cost ratio by the coefficients in the table below. Category Outdoor piping (inside culvert) Toilet Mechanical room Standard market unit price 0.90 1.20 1.30 Labor cost ratio 1.00 1.00 1.00

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.