DE330.11000

Mechanical excavation/Soft rock/5m or less

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
Good
Unit
m3
H2 2026 Unit Price
37,634 KRW
Labor Ratio
48 %

Unit Price Definition

① Based on mechanical excavation (including crushing and lifting out) according to rock/soil condition, depth, and working conditions. ② Classification by specification (working condition) shall be applied as follows. - Good: where continuous work is possible and there is no interference with lifting-out work - Poor: conditions where continuous work is difficult and work interference occurs due to obstacles, temporary works, etc. ③ Excludes shoring, dewatering, and loading and hauling costs for off-site disposal of excavated soil. ④ The volume conversion factor is already reflected and applies to soil quantity in natural condition.

Unit Price Adjustment

- Apply by multiplying the following coefficients according to groundwater occurrence. Category Standard market unit price Labor cost ratio Land 1.00 1.00 Groundwater 1.33 1.00

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.