Plain concrete placing / Pump truck
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- TYPE-4
- Unit
- m3
- H2 2026 Unit Price
- 72,207 KRW
- Labor Ratio
- 58 %
Unit Price Definition
① Based on concrete placement work by concrete pump truck (80m3/hr or more) (boom placing, slump 15). ② This is the cost for one day of placement for a single structure (including setup and finishing), and includes cases where two or more adjacent structures are placed continuously within the daily working hours. ③ Includes placement preparation and cleanup, pump truck placing (setup and finishing), compaction, and curing preparation work. ④ Excludes ready-mixed concrete material cost, and curing and surface finishing costs after concrete placement. ⑤ Material cost for residual concrete generated after placement (residue inside piping, etc.) shall be calculated separately. ⑥ This unit price shall not be applied when placement must be carried out by pipeline. ⑦ Refer below for the applicable type by specification. Classification Type TYPE-1 Structures such as mat foundations with no restrictions on pump truck operation TYPE-2 General structures such as walls, columns, beams, slabs, abutments, and piers TYPE-3 Structures with narrow or deep placing areas that restrict pump truck operation, such as strip foundations, columns and beams of [wall girder] structures without slabs TYPE-4 Structures constructed on cut/fill slopes where pump truck movement is frequent, etc., and pump truck operation is severely restricted
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.