Slope trimming of earth cut
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- Medium rock・Hard rock
- Unit
- m2
- H2 2026 Unit Price
- 15,981 KRW
- Labor Ratio
- 66 %
Unit Price Definition
① Based on slope trimming work for the cut section using an excavator (breaker).
Unit Price Adjustment
- Where cobbles, boulders, gravel, etc. are mixed and there are constraints on slope trimming, apply by multiplying the following coefficients. Category Standard market unit price Labor cost ratio Soil 1.00 1.00 Mixed soil 1.64 1.01
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.