Embankment in front of abutment
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- -
- Unit
- m3
- H2 2026 Unit Price
- 7,165 KRW
- Labor Ratio
- 87 %
Unit Price Definition
① Based on embankment work in front of bridge abutments. ② Includes machine spreading, watering, and compaction cost for embankment material required during embankment construction. ③ Material cost and transport cost of embankment material are excluded.
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.