This service is available to members only.

GA415.00900

Polyester resin concrete pipe / Socket type

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
∅900mm
Unit
m
H2 2026 Unit Price
118,170 KRW
Labor Ratio
77 %

Unit Price Definition

① Based on socket-type jointing of polyester resin concrete pipe (PRC pipe, 2.5m). ② Includes pipe laying and jointing, cutting, and unloading of materials; excavation, backfilling, dewatering, surplus soil disposal, and foundation work for the pipeline are excluded. ③ Purchase and transportation costs of polyester resin concrete pipe and rubber rings are excluded, while the cost of consumable materials (joint mortar, etc.) is included. ④ Tool loss and miscellaneous materials are included.

Unit Price Adjustment

- Pipe works are carried out under conditions affected by earthworks (excavation and restoration work, etc.); therefore, the following coefficients shall be applied in consideration of site construction conditions. Category Standard market unit price Labor ratio - Site where construction is performed under the impact of same-day excavation and restoration work - Case where continuous excavation is impossible due to traffic restrictions, temporary shoring, obstacles (buried objects, etc.), etc., so excavation, pipe laying, and jointing are carried out repeatedly in parallel 1.00 1.00 - Site where construction is performed under the impact of same-day excavation and restoration work 0.75 1.00 - Case where excavation work is carried out separately in advance and laying and jointing are continuously performed - Site where construction is performed without the impact of excavation and restoration work - Case where laying and jointing alone are performed in an open-cut section with preceding work (excavation work or foundation work) completed 0.50 1.00

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.