Impact-resistant water pipe / socket type
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- ∅200mm
- Unit
- m
- H2 2026 Unit Price
- 10,169 KRW
- Labor Ratio
- 83 %
Unit Price Definition
① Based on socket-type jointing of impact-resistant water pipe (impact-resistant rigid polyvinyl chloride pipe (HIVP), 6m / pressure pipe). ② Includes pipe laying and jointing, cutting, and material unloading work; excludes trench excavation, backfilling, dewatering, surplus soil disposal, and foundation work for the pipeline. ③ Installation of separation-prevention device (one-sided separation-prevention pressure ring) is excluded. ④ Purchase and transport costs of impact-resistant water pipe and rubber ring, and hydrostatic test costs are excluded.
Unit Price Adjustment
- Pipe works are carried out under conditions affected by earthworks (excavation and restoration work, etc.); therefore, the following coefficients shall be applied in consideration of site construction conditions. Category Standard market unit price Labor ratio - Site where construction is performed under the impact of same-day excavation and restoration work - Case where continuous excavation is impossible due to traffic restrictions, temporary shoring, obstacles (buried objects, etc.), etc., so excavation, pipe laying, and jointing are carried out repeatedly in parallel 1.00 1.00 - Site where construction is performed under the impact of same-day excavation and restoration work 0.75 1.00 - Case where excavation work is carried out separately in advance and laying and jointing are continuously performed - Site where construction is performed without the impact of excavation and restoration work - Case where laying and jointing alone are performed in an open-cut section with preceding work (excavation work or foundation work) completed 0.50 1.00
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.