This service is available to members only.

HC311.02020

Precast heavy structure

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
1,150kg/unit or more ~ less than 1,500kg/unit
Unit
ea
H2 2026 Unit Price
108,488 KRW
Labor Ratio
74 %

Unit Price Definition

① Based on installation of precast heavy structure (drop structure, fountain pipe, L-shaped flume, others). ② Includes heavy structure installation and joint mortar finishing. ③ Excavation, foundation (concrete, gravel, sand), ground leveling, and backfilling work are excluded. ④ Includes consumable material cost (joint mortar, etc.). ⑤ Material cost of heavy structure is excluded.

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.