Precast heavy structure
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- 2,000kg/unit or more ~ less than 2,500kg/unit
- Unit
- ea
- H2 2026 Unit Price
- 171,359 KRW
- Labor Ratio
- 74 %
Unit Price Definition
① Based on installation of precast heavy structure (drop structure, fountain pipe, L-shaped flume, others). ② Includes heavy structure installation and joint mortar finishing. ③ Excavation, foundation (concrete, gravel, sand), ground leveling, and backfilling work are excluded. ④ Includes consumable material cost (joint mortar, etc.). ⑤ Material cost of heavy structure is excluded.
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.