Concrete pile head trimming
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- D700mm
- Unit
- pc
- H2 2026 Unit Price
- 32,601 KRW
- Labor Ratio
- 85 %
Unit Price Definition
① Based on the work of cutting the pile head to the design elevation after completion of concrete pile installation, using a grinder. ② Includes pile cutting, worksite cleanup, and finishing work, but excludes crushing of the cut pile head. ③ Includes miscellaneous materials and consumables (grinder blade, iron wire, pile cap, etc.). ④ Costs required for pile head reinforcement are excluded.
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.