This service is available to members only.

KD201.01000

Bridge drainage facilities

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
∅150~250㎜
Unit
m
H2 2026 Unit Price
97,840 KRW
Labor Ratio
83 %

Unit Price Definition

① Based on installation work for pre-manufactured materials for exposed bridge drain pipes. ② Includes installation of support metal fittings, cutting and joining of drain pipes (straight pipes, curved pipes), and caulking work. ③ Installation of drain inlets, catch basins, and buried drain pipes is excluded. ④ Material cost (drainage facilities, etc.) is excluded. 【Reference】 - For the application range of drainage facilities, refer to the following. <Applicable to drain pipes excluding drain inlets and catch basins> <Length calculated along the centerline>

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.