LH221.00000

Road stud

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
-
Unit
nr (location)
H2 2026 Unit Price
5,322 KRW
Labor Ratio
95 %

Unit Price Definition

① This is based on installation work for road studs attached by drilling into the pavement surface. ② Includes drilling, adhesive application, and road stud installation. ③ Material costs (road studs, etc.) are excluded. ④ Miscellaneous material and consumable material costs (adhesive, etc.) are included.

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.