NS033.01000

Surface preparation for concrete/mortar surfaces

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
Ceiling
Unit
m2
H2 2026 Unit Price
3,127 KRW
Labor Ratio
98 %

Unit Price Definition

① This standard applies to surface preparation work for painting on concrete/mortar surfaces. ② Includes substrate preparation and cleaning, puttying, and sanding work. ③ Concrete fair-face finishing, finish plastering, and primer coating shall be measured separately. ④ Material costs (putty, etc.) are excluded.

Unit Price Adjustment

- When scaffolding is used, apply the following coefficients in the table below to the unit price and labor cost ratio according to height. Category Standard market unit price Labor cost ratio 1st to 3rd floor 1.00 1.00 4th to 6th floor 1.05 1.00 7th to 9th floor 1.08 1.00 10th to 12th floor 1.12 1.00 13th to 15th floor 1.16 1.00 16th to 18th floor 1.20 1.00 Above 19th floor add 0.04 for every increase of 3 floors 1.00 ※ If floors cannot be distinguished from the exterior wall, convert the number of floors based on a floor height of 3.6m, and for interior wall height as well, convert and apply based on 3.6m.

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.