OH400.00200

Block facing / River embankment

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
Equipment construction
Unit
m2
H2 2026 Unit Price
8,795 KRW
Labor Ratio
82 %

Unit Price Definition

① This unit price is the standard for installing revetment blocks on river embankments. ② It includes installation of revetment blocks and hardware connection work. ③ Material cost (blocks, hardware, etc.) is excluded. ④ If slope trimming, earth filling, and turfing are required, they shall be separately estimated.

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.