This service is available to members only.

AA270.02010

Installation and dismantling of falling-object protection net

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
Steel pipe (3 months or less)
Unit
m2
H2 2026 Unit Price
11,579 KRW
Labor Ratio
78 %

Unit Price Definition

① This is based on the installation and dismantling of a falling-object protection net (horizontal direction 3m or less) using steel pipes on the exterior of building scaffolding. ② It includes the installation and dismantling of the support frame and netting. ③ It includes the protection-net support frame (steel pipe (∅48.6mm×2.4mm), brackets, clamps, etc.) and consumable material costs, but excludes the material cost of the falling-object protection net.

Unit Price Adjustment

- If the construction period exceeds 3 months, apply by multiplying the following coefficients. Falling-object protection work 3 months or less 6 months or less 12 months or less Standard market unit price 1.00 1.10 1.31 Labor ratio 1.00 0.91 0.76

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.