Natural fiber mat installation
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- -
- Unit
- m2
- H2 2026 Unit Price
- 3,494 KRW
- Labor Ratio
- 98 %
Unit Price Definition
① Based on natural fiber mat work on earthwork slopes (slope gradient 1:1.0~1.5, height 30m or less). ② Includes manual earth leveling and mat laying work. ③ Slope finishing is excluded. ④ Material cost (natural fiber mat, fixing pins, etc.) is excluded. ⑤ Incidental material cost (vinyl string, etc.) is included.
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.