DI610.00001

Backfilling and compaction

Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652

Specification
Large equipment
Unit
m3
H2 2026 Unit Price
8,822 KRW
Labor Ratio
67 %

Unit Price Definition

① Based on backfill work for structures, and includes spreading, leveling, compaction, and watering work. ② Large equipment is based on the combined use of a vibratory roller (10ton class) and a small hand-guided roller (0.7ton). ③ Small equipment applies to work in narrow sections where the use of large equipment (vibratory roller) is difficult. ④ Material cost and transport cost of backfill material, and bearing capacity test cost are excluded. ⑤ The volume conversion factor has already been reflected and is applied to soil volume in the compacted state.

This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.