Concrete placing / Equipment use
Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price for Construction Works · MOLIT Public Notice No. 2026-652
- Specification
- Plain concrete
- Unit
- m3
- H2 2026 Unit Price
- 28,142 KRW
- Labor Ratio
- 80 %
Unit Price Definition
① Based on work in which concrete is supplied from a mixer truck to an excavator and directly placed at the pouring location. ② Includes on-site concrete transport, placing, compaction, and curing preparation work. ③ Ready-mixed concrete material cost, curing after concrete placement, and surface finishing costs are excluded. ④ For small structures, apply when the placing locations with small quantities (12m3 or less per location) are scattered by site.
Unit Price Adjustment
- When constructing small structures (12m3 or less per location), if equipment access is impossible and manual transport placing is required, apply by multiplying by the following coefficients. Category Standard market unit price Labor cost ratio Equipment-use placing 1.00 1.00 Manual-transport placing 2.00 1.22 ※ Manual-transport placing is based on construction by transporting concrete using manual transport equipment (wheelbarrows, etc.).
This page is organized from the Ministry of Land, Infrastructure and Transport (MOLIT) H2 2026 Standard Market Price notice data for construction works for search and reference purposes. For actual estimated price calculation and quotations, please be sure to review both the original notice and site conditions together.